Court Farm, Stockton Court, Stockton,, Hereford and Worcester, WR6 6UT
Stockton Court Farm is a 5 MW solar farm project in West Midlands. The applicant or operator on record is Renewable Power Exchange. The application has been withdrawn or the scheme abandoned. The determining authority is Malvern Hills, reference 16/00678/FUL.β¦
Withdrawn
Project stageWithdrawn / abandoned
PlanningApr 2016 (completed)
Withdrawn / abandoned (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Application Withdrawn.
Official register: July 2026
Recorded status: Planning Application Withdrawn. Source record updated 2017-06-01.
Registered planning capacity; not measured generation.
Stockton Court Farm is a 5 MW solar farm project in West Midlands. The applicant or operator on record is Renewable Power Exchange. The application has been withdrawn or the scheme abandoned. The determining authority is Malvern Hills, reference 16/00678/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Renewable Power Exchange
Owner / operator
Renewable Power Exchange