South West Of Station Road, Fiddlers Ferry, Penketh, Cheshire, WA5 2UJ
Station Road, Fiddlers Ferry - Battery Energy Storage is a 250 MW battery storage project in North West. The applicant or operator on record is Net Zero One Limited. The planning application was refused. The determining authority is Warrington, reference 2025/00999/FULM.β¦
Refused
Project stageRefused
PlanningJul 2025 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Refused.
Official register: July 2026
Recorded status: Planning Permission Refused. Source record updated 2025-12-16.
Registered planning capacity; not measured generation.
Station Road, Fiddlers Ferry - Battery Energy Storage is a 250 MW battery storage project in North West. The applicant or operator on record is Net Zero One Limited. The planning application was refused. The determining authority is Warrington, reference 2025/00999/FULM.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
250.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Net Zero One Limited
Owner / operator
Net Zero One Limited
Location
South West Of Station Road, Fiddlers Ferry, Penketh, Cheshire, WA5 2UJ