Stanstead Solar Project is a 14.3 MW solar farm project in Eastern. The applicant or operator on record is Manchester Airport Group Plc. It is recorded as under construction since January 2025. The determining authority is Uttlesford, reference S62A/22/0000004.…

Under Construction
Project stageUnder construction
  1. PlanningJun 2022 (completed)
  2. ConsentedAug 2022 (completed)
  3. ConstructionJan 2025 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2025-03-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

14.300 MW
Registered Capacity

πŸ“‹ Project Overview

Stanstead Solar Project is a 14.3 MW solar farm project in Eastern. The applicant or operator on record is Manchester Airport Group Plc. It is recorded as under construction since January 2025. The determining authority is Uttlesford, reference S62A/22/0000004.

Site Schematic

SUBSTATION ? ha Β· 14.3 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)14.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperManchester Airport Group Plc
Owner / operatorManchester Airport Group Plc
Year consented2022
Construction started2025
LocationE/O Coopers End Road, Essex, CM22 6PL
RegionEastern
Coordinates51.8879295Β°N, 0.2656654Β°E

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)225000

πŸ“… Project Timeline

2022-06-01
2022-08-24
2025-01-01