Stairfoot Battery Storage Facility is a battery storage project in Yorkshire and Humber. The applicant or operator on record is Noriker Power Limited. It is recorded as operational since July 2021. The determining authority is Barnsley, reference 2020/1373.β¦
OperationalΒ· Since 2021
Project stageOperating
PlanningJan 2021 (completed)
ConsentedNov 2022 (completed)
Construction (completed)
OperatingJul 2021 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2021-02-08.
Registered planning capacity; not measured generation.
Stairfoot Battery Storage Facility is a battery storage project in Yorkshire and Humber. The applicant or operator on record is Noriker Power Limited. It is recorded as operational since July 2021. The determining authority is Barnsley, reference 2020/1373.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Noriker Power Limited
Owner / operator
Noriker Power Limited
Year consented
2022
Commissioned / target
2021