St Johns Wells Wind Cluster Extension is a 3.2 MW onshore wind project in Scotland. The applicant or operator on record is Green Cat Renewables. It is recorded as operational since March 2015. The determining authority is Aberdeenshire, reference APP/2009/4121.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningJan 2010 (completed)
ConsentedJun 2012 (completed)
ConstructionOct 2013 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-03-05.
Registered planning capacity; not measured generation.
St Johns Wells Wind Cluster Extension is a 3.2 MW onshore wind project in Scotland. The applicant or operator on record is Green Cat Renewables. It is recorded as operational since March 2015. The determining authority is Aberdeenshire, reference APP/2009/4121.