Onshore Wind

Srondoire Community Wind Farm

Cruach A Phubuill, Adj Allt Dearg Windfarm, Ardrishaig, Lochgilphead, Argyll, PA31 8PE, Strathclyde

Srondoire Community Wind Farm is a 6 MW onshore wind project in Scotland. The applicant or operator on record is Srondoire Wind Farmers LLP. It is recorded as operational since December 2015. The determining authority is Argyll and Bute, reference 13/01427/PP.…

Operational Β· Since 2015
Project stageOperating
  1. PlanningJul 2013 (completed)
  2. ConsentedDec 2013 (completed)
  3. ConstructionJun 2014 (completed)
  4. OperatingDec 2015 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-04-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.000 MW
Registered Capacity
2015
Commissioned

πŸ“‹ Project Overview

Srondoire Community Wind Farm is a 6 MW onshore wind project in Scotland. The applicant or operator on record is Srondoire Wind Farmers LLP. It is recorded as operational since December 2015. The determining authority is Argyll and Bute, reference 13/01427/PP.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSrondoire Wind Farmers LLP
Owner / operatorSrondoire Wind Farmers LLP
Year consented2013
Construction started2014
Commissioned / target2015
LocationCruach A Phubuill, Adj Allt Dearg Windfarm, Ardrishaig, Lochgilphead, Argyll, PA31 8PE, Strathclyde
RegionScotland
Coordinates55.9341008Β°N, 5.4805222Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2
No. of Turbines3

πŸ“… Project Timeline

2013-07-10
2013-12-11
2014-06-20
2015-12-20