Proposed Solar Park Southwick Estate, Belney Lane, Southwick, Hampshire, Hampshire, PO17 6ET
Southwick Estate is a 48 MW solar farm project in South East. The applicant or operator on record is Bluefield Solar Income Fund. It is recorded as operational since March 2015. The determining authority is Winchester, reference 13/02304/FUL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningOct 2013 (completed)
ConsentedDec 2013 (completed)
ConstructionDec 2014 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-03-17.
Registered planning capacity; not measured generation.
Southwick Estate is a 48 MW solar farm project in South East. The applicant or operator on record is Bluefield Solar Income Fund. It is recorded as operational since March 2015. The determining authority is Winchester, reference 13/02304/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
48.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Bluefield Solar Income Fund
Owner / operator
Bluefield Solar Income Fund
Year consented
2013
Construction started
2014
Commissioned / target
2015
Location
Proposed Solar Park Southwick Estate, Belney Lane, Southwick, Hampshire, Hampshire, PO17 6ET