Agricultural field to the sout, Burneside, Kendal, Cumbria, LA9 6PU
South Stilling Tanks Solar Farm is a 0.5 MW solar farm project in North West. The applicant or operator on record is Ellergreen Energy. It is recorded as operational since December 2021. The determining authority is Westmorland and Furness, reference SL/2020/0391.β¦
OperationalΒ· Since 2021
Project stageOperating
PlanningSep 2020 (completed)
ConsentedApr 2021 (completed)
ConstructionAug 2021 (completed)
OperatingDec 2021 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2023-07-03.
Registered planning capacity; not measured generation.
South Stilling Tanks Solar Farm is a 0.5 MW solar farm project in North West. The applicant or operator on record is Ellergreen Energy. It is recorded as operational since December 2021. The determining authority is Westmorland and Furness, reference SL/2020/0391.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Ellergreen Energy
Owner / operator
Ellergreen Energy
Year consented
2021
Construction started
2021
Commissioned / target
2021
Location
Agricultural field to the sout, Burneside, Kendal, Cumbria, LA9 6PU