Solar Farm

South Antrim Solar Park - Phase 1

Lands approx 550m South of, 99 Dublin Road, Antrim, Co. Antrim, BT41 4PN

South Antrim Solar Park - Phase 1 is a 6.5 MW solar farm project in Northern Ireland. The applicant or operator on record is Hadstone Energy. It is recorded as operational since May 2018. The determining authority is Antrim and Newtownabbey, reference LA03/2015/0262/F.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningJun 2015 (completed)
  2. ConsentedApr 2016 (completed)
  3. ConstructionMar 2018 (completed)
  4. OperatingMay 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-01-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.500 MW
Registered Capacity
2018
Commissioned

πŸ“‹ Project Overview

South Antrim Solar Park - Phase 1 is a 6.5 MW solar farm project in Northern Ireland. The applicant or operator on record is Hadstone Energy. It is recorded as operational since May 2018. The determining authority is Antrim and Newtownabbey, reference LA03/2015/0262/F.

Site Schematic

SUBSTATION ? ha Β· 6.5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHadstone Energy
Owner / operatorHadstone Energy
Year consented2016
Construction started2018
Commissioned / target2018
LocationLands approx 550m South of, 99 Dublin Road, Antrim, Co. Antrim, BT41 4PN
RegionNorthern Ireland
Coordinates54.6943473Β°N, 6.2341485Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)798000

πŸ“… Project Timeline

2015-06-30
2016-04-26
2018-03-10
2018-05-10