Land North Of Sober Hill Farm Stoneknowle Hill North Newbald, Humberside
Sober Hill Wind Farm is a 15 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is West Coast Energy. It is recorded as operational since September 2013. The determining authority is East Riding of Yorkshire, reference 08/04816/STPLFE.β¦
OperationalΒ· Since 2013
Project stageOperating
PlanningOct 2008 (completed)
ConsentedMar 2010 (completed)
ConstructionMar 2012 (completed)
OperatingSep 2013 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2014-08-20.
Registered planning capacity; not measured generation.
Sober Hill Wind Farm is a 15 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is West Coast Energy. It is recorded as operational since September 2013. The determining authority is East Riding of Yorkshire, reference 08/04816/STPLFE.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
15.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
West Coast Energy
Owner / operator
West Coast Energy
Year consented
2010
Construction started
2012
Commissioned / target
2013
Location
Land North Of Sober Hill Farm Stoneknowle Hill North Newbald, Humberside