Battery Storage

Soay Solar Farm and Greener Grid Park

Three Cocked Hat Plantation, Waplington Lane, Allerthorpe, York, North Yorkshire, YO42 4RL

Soay Solar Farm and Greener Grid Park is a 200 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Statkraft Uk Limited. It is recorded as under construction since September 2025. The determining authority is East Riding of Yorkshire, refere…

Under Construction
Project stageUnder construction
  1. PlanningJan 2022 (completed)
  2. ConsentedNov 2022 (completed)
  3. ConstructionSep 2025 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2026-03-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

200.000 MW
Power Capacity

πŸ“‹ Project Overview

Soay Solar Farm and Greener Grid Park is a 200 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Statkraft Uk Limited. It is recorded as under construction since September 2025. The determining authority is East Riding of Yorkshire, reference 21/04505/STPLF.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)200.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperStatkraft Uk Limited
Owner / operatorStatkraft Uk Limited
Year consented2022
Construction started2025
LocationThree Cocked Hat Plantation, Waplington Lane, Allerthorpe, York, North Yorkshire, YO42 4RL
RegionYorkshire and Humber
Coordinates53.9068247Β°N, 0.8075835Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID9014

πŸ“… Project Timeline

2022-01-26
2022-11-28
2025-09-01