πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Snetterton Biomass Plant

Snetterton Heath, near the A11 in Snetterton, Norfolk, NR16 2JU

Snetterton Biomass Plant is a 44.2 MW bioenergy / waste project in Eastern. The applicant or operator on record is Burmeister & Wain Scandinavian Contractor A/S (BWSC). It is recorded as operational since December 2016. The determining authority is Breckland, reference 3PL/2012/0…

Operational Β· Since 2016
Project stageOperating
  1. PlanningJan 2012 (completed)
  2. ConsentedJul 2012 (completed)
  3. ConstructionJan 2015 (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2017-11-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

44.200 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Snetterton Biomass Plant is a 44.2 MW bioenergy / waste project in Eastern. The applicant or operator on record is Burmeister & Wain Scandinavian Contractor A/S (BWSC). It is recorded as operational since December 2016. The determining authority is Breckland, reference 3PL/2012/0029/F.

πŸ”§ Technical Specifications

Capacity (MW)44.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBurmeister & Wain Scandinavian Contractor A/S (BWSC)
Owner / operatorBurmeister & Wain Scandinavian Contractor A/S (BWSC)
Year consented2012
Construction started2015
Commissioned / target2016
LocationSnetterton Heath, near the A11 in Snetterton, Norfolk, NR16 2JU
RegionEastern
Coordinates52.4791482Β°N, 0.9544345Β°E

Additional published register fields

Registered technologyBiomass (dedicated)

πŸ“… Project Timeline

2012-01-19
2012-07-18
2015-01-20