Battery Storage

Smarter Network Storage

Leighton Buzzard, Bedfordshire, Bedfordshire, LU7 3NU

Smarter Network Storage is a 6 MW battery storage project in Eastern. The applicant or operator on record is UK Power Networks. The scheme is currently in the planning system. The determining authority is Central Bedfordshire.…

Decommissioned Β· Target 2014
Project stageClosed
  1. Planning (completed)
  2. Consented (completed)
  3. ConstructionMay 2014 (completed)
  4. OperatingDec 2014 (completed)
  5. Closed (current stage)

Status in the official register: Decommissioned.

Official register: July 2026

Recorded status: Decommissioned. Source record updated 2018-10-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.000 MW
Power Capacity
2014
Target Date

πŸ“‹ Project Overview

Smarter Network Storage is a 6 MW battery storage project in Eastern. The applicant or operator on record is UK Power Networks. The scheme is currently in the planning system. The determining authority is Central Bedfordshire.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperUK Power Networks
Owner / operatorUK Power Networks
Construction started2014
Commissioned / target2014
LocationLeighton Buzzard, Bedfordshire, Bedfordshire, LU7 3NU
RegionEastern
Coordinates51.9165777Β°N, 0.6527756Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2014-05-15
2014-12-12