πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Slough Road - Battery Storage

Northern Part Of Former Woodlands Park Landfill Site, S/o Slough Road, Iver Heath, Iver, Buckinghamshire, SL0 0EA

Slough Road - Battery Storage is a 57 MW battery storage project in South East. The applicant or operator on record is Pivot Power. The application has been withdrawn or the scheme abandoned. The determining authority is Buckinghamshire, reference PL/21/3644/FA.…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningSep 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Application Withdrawn.

Official register: July 2026

Recorded status: Planning Application Withdrawn. Source record updated 2023-01-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

57.000 MW
Power Capacity

πŸ“‹ Project Overview

Slough Road - Battery Storage is a 57 MW battery storage project in South East. The applicant or operator on record is Pivot Power. The application has been withdrawn or the scheme abandoned. The determining authority is Buckinghamshire, reference PL/21/3644/FA.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)57.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPivot Power
Owner / operatorPivot Power
LocationNorthern Part Of Former Woodlands Park Landfill Site, S/o Slough Road, Iver Heath, Iver, Buckinghamshire, SL0 0EA
RegionSouth East
Coordinates51.5381745Β°N, 0.5073845Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-09-29