Sidegate Lane Landfill Site is a 1.3 MW bioenergy / waste project in East Midlands. The applicant or operator on record is East Midlands Electricity Generation. It is recorded as operational since August 1996. The determining authority is North Northamptonshire.…

Operational Β· Since 1996
Project stageOperating
  1. PlanningApr 1995 (completed)
  2. ConsentedJun 1995 (completed)
  3. Construction (completed)
  4. OperatingAug 1996 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2011-10-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.300 MW
Registered Capacity
1996
Commissioned

πŸ“‹ Project Overview

Sidegate Lane Landfill Site is a 1.3 MW bioenergy / waste project in East Midlands. The applicant or operator on record is East Midlands Electricity Generation. It is recorded as operational since August 1996. The determining authority is North Northamptonshire.

πŸ”§ Technical Specifications

Capacity (MW)1.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEast Midlands Electricity Generation
Owner / operatorEast Midlands Electricity Generation
Year consented1995
Commissioned / target1996
LocationSidegate Lane Landfill Site , Finedon , near Wellingborough , Northants, Northamptonshire
RegionEast Midlands
Coordinates52.3231809Β°N, 0.6589048Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1995-04-26
1995-06-09
1996-08-01