Shoreham Renewable Energy Generation project

E/O Shoreham Power Station, Basin Road, Southwick, Brighton,, West Sussex, BN41 1WF

Shoreham Renewable Energy Generation project is a 32 MW bioenergy / waste project in South East. The applicant or operator on record is Edgeley Green Power (EGP). The application has been withdrawn or the scheme abandoned. The determining authority is Adur, reference AWDM/0868/12…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningJul 2012 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedMay 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Abandoned.

Official register: July 2026

Recorded status: Abandoned. Source record updated 2017-03-27.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

32.000 MW
Registered Capacity

πŸ“‹ Project Overview

Shoreham Renewable Energy Generation project is a 32 MW bioenergy / waste project in South East. The applicant or operator on record is Edgeley Green Power (EGP). The application has been withdrawn or the scheme abandoned. The determining authority is Adur, reference AWDM/0868/12.

πŸ”§ Technical Specifications

Capacity (MW)32.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEdgeley Green Power (EGP)
Owner / operatorEdgeley Green Power (EGP)
Year consented2013
LocationE/O Shoreham Power Station, Basin Road, Southwick, Brighton,, West Sussex, BN41 1WF
RegionSouth East
Coordinates50.8291951Β°N, 0.2205095Β°W

Additional published register fields

Registered technologyBiomass (dedicated)

πŸ“… Project Timeline

2012-07-13
2013-05-07