Landfill Site Shewalton Road, Riverside Business Park, Irvine, Ayrshire, KA11 5AW
Shewalton Landfill Solar Farm is a 5 MW solar farm project in Scotland. The applicant or operator on record is North Ayrshire Council. It is recorded as under construction since February 2024. The determining authority is North Ayrshire, reference 23/00318/PP.β¦
Under Construction
Project stageUnder construction
PlanningMay 2023 (completed)
ConsentedJun 2023 (completed)
ConstructionFeb 2024 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2024-02-13.
Registered planning capacity; not measured generation.
Shewalton Landfill Solar Farm is a 5 MW solar farm project in Scotland. The applicant or operator on record is North Ayrshire Council. It is recorded as under construction since February 2024. The determining authority is North Ayrshire, reference 23/00318/PP.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
North Ayrshire Council
Owner / operator
North Ayrshire Council
Year consented
2023
Construction started
2024
Location
Landfill Site Shewalton Road, Riverside Business Park, Irvine, Ayrshire, KA11 5AW