Sharpness Docks is a 2 MW onshore wind project in South West. The applicant or operator on record is Partnerships for Renewables/AGR. It is recorded as operational since January 2017. The determining authority is Stroud, reference S.11/2448/FUL.…

Operational Β· Since 2017
Project stageOperating
  1. PlanningDec 2011 (completed)
  2. ConsentedMay 2014 (completed)
  3. ConstructionNov 2016 (completed)
  4. OperatingJan 2017 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2018-05-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity
2017
Commissioned

πŸ“‹ Project Overview

Sharpness Docks is a 2 MW onshore wind project in South West. The applicant or operator on record is Partnerships for Renewables/AGR. It is recorded as operational since January 2017. The determining authority is Stroud, reference S.11/2448/FUL.

Site Schematic

SOUTH WEST Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPartnerships for Renewables/AGR
Owner / operatorPartnerships for Renewables/AGR
Year consented2014
Construction started2016
Commissioned / target2017
LocationDock Lane, Sharpness, Berkley, Gloucestershire, Gloucestershire
RegionSouth West
Coordinates51.7229718Β°N, 2.4809345Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2
No. of Turbines1

πŸ“… Project Timeline

2011-12-05
2014-05-19
2016-11-15
2017-01-15