πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Sewage Pumping Station - Micro Energy Storage

Sewage Pumping Station, Broad Lane, Cambridge, Cambridgeshire, CB24 8XN

Sewage Pumping Station - Micro Energy Storage is a 0.2 MW battery storage project in Eastern. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of September 2024 and it is awaiting construction. The determining authority is East Camb…

Consented / Approved
Project stageConsented
  1. PlanningAug 2024 (completed)
  2. ConsentedSep 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-10-08.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.200 MW
Power Capacity

πŸ“‹ Project Overview

Sewage Pumping Station - Micro Energy Storage is a 0.2 MW battery storage project in Eastern. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of September 2024 and it is awaiting construction. The determining authority is East Cambridgeshire, reference 24/02975/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.200 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAMP Clean Energy
Owner / operatorAMP Clean Energy
Year consented2024
LocationSewage Pumping Station, Broad Lane, Cambridge, Cambridgeshire, CB24 8XN
RegionEastern
Coordinates52.2925558Β°N, 0.122384Β°E

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-08-12