πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Severn Trent STW

Fillingate, Wanlip, Leicester, Leicestershire, LE7 4PF

Severn Trent STW is a 2.5 MW onshore wind project in East Midlands. The applicant or operator on record is Severn Trent Water. It is recorded as operational since February 2014. The determining authority is Charnwood, reference P/09/2402/2.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningDec 2009 (completed)
  2. ConsentedMar 2011 (completed)
  3. ConstructionNov 2013 (completed)
  4. OperatingFeb 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2014-02-27.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.500 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Severn Trent STW is a 2.5 MW onshore wind project in East Midlands. The applicant or operator on record is Severn Trent Water. It is recorded as operational since February 2014. The determining authority is Charnwood, reference P/09/2402/2.

Site Schematic

EAST MIDLANDS Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSevern Trent Water
Owner / operatorSevern Trent Water
Year consented2011
Construction started2013
Commissioned / target2014
LocationFillingate, Wanlip, Leicester, Leicestershire, LE7 4PF
RegionEast Midlands
Coordinates52.6980472Β°N, 1.1178775Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.5
No. of Turbines1

πŸ“… Project Timeline

2009-12-21
2011-03-16
2013-11-01
2014-02-26