Project be sited in an area of 25 metre deep open sea known as the Skerries, off the north-west coast of Anglesey, Offshore
SeaGen Wales Tidal Farm is a 10 MW tidal stream project in Offshore. The applicant or operator on record is Marine Current Turbines (MCT) / NPower. The application has been withdrawn or the scheme abandoned. The determining authority is DECC (S36), reference 18C201.β¦
Withdrawn
Project stageWithdrawn / abandoned
PlanningMar 2011 (completed)
Withdrawn / abandoned (project stopped here)
ConsentedFeb 2013 (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Abandoned.
Official register: July 2026
Recorded status: Abandoned. Source record updated 2014-09-19.
Registered planning capacity; not measured generation.
SeaGen Wales Tidal Farm is a 10 MW tidal stream project in Offshore. The applicant or operator on record is Marine Current Turbines (MCT) / NPower. The application has been withdrawn or the scheme abandoned. The determining authority is DECC (S36), reference 18C201.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
10.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Marine Current Turbines (MCT) / NPower
Owner / operator
Marine Current Turbines (MCT) / NPower
Year consented
2013
Location
Project be sited in an area of 25 metre deep open sea known as the Skerries, off the north-west coast of Anglesey, Offshore