Solar Farm

Sea Farm Piggery, Marshchapel - Solar Panels

Sea Farm Piggery, North Lane, Marshchapel, Lincolnshire, DN36 5UF

Sea Farm Piggery, Marshchapel - Solar Panels is a 0.16 MW solar farm project in East Midlands. The applicant or operator on record is York Wold Pig Pro Limited. Planning permission has been granted as of April 2024 and it is awaiting construction. The determining authority is Eas…

Consented / Approved
Project stageConsented
  1. PlanningMar 2024 (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-03-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.160 MW
Registered Capacity

πŸ“‹ Project Overview

Sea Farm Piggery, Marshchapel - Solar Panels is a 0.16 MW solar farm project in East Midlands. The applicant or operator on record is York Wold Pig Pro Limited. Planning permission has been granted as of April 2024 and it is awaiting construction. The determining authority is East Lindsey, reference N/118/00391/24.

Site Schematic

SUBSTATION ? ha Β· 0.16 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.160 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperYork Wold Pig Pro Limited
Owner / operatorYork Wold Pig Pro Limited
Year consented2024
LocationSea Farm Piggery, North Lane, Marshchapel, Lincolnshire, DN36 5UF
RegionEast Midlands
Coordinates53.4805622Β°N, 0.0624811Β°E

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarRoof

πŸ“… Project Timeline

2024-03-05
2024-04-26