Former RAF Coltishall, Coltishall Airfield, Filby Road, Norwich, Norfolk, Norfolk
Scottow Moor - RAF Coltishall Solar Farm (Phase 2) is a 17.9 MW solar farm project in Eastern. The applicant or operator on record is Greencoat Capital. It is recorded as operational since March 2016. The determining authority is North Norfolk, reference PF/14/1334.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningOct 2014 (completed)
ConsentedDec 2014 (completed)
ConstructionJan 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-04-04.
Registered planning capacity; not measured generation.
Scottow Moor - RAF Coltishall Solar Farm (Phase 2) is a 17.9 MW solar farm project in Eastern. The applicant or operator on record is Greencoat Capital. It is recorded as operational since March 2016. The determining authority is North Norfolk, reference PF/14/1334.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
17.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Greencoat Capital
Owner / operator
Greencoat Capital
Year consented
2014
Construction started
2016
Commissioned / target
2016
Location
Former RAF Coltishall, Coltishall Airfield, Filby Road, Norwich, Norfolk, Norfolk