SAS International Parc Crescent Waterton Industrial Estate, Bridgend, Mid Glamorgan, CF31 3XU
SAS International, Unit 1 - Solar PV Panels is a 0.8 MW solar farm project in Wales. The applicant or operator on record is SAS International Limited. It is recorded as under construction since May 2022. The determining authority is Bridgend, reference P/21/765/FUL.β¦
Under Construction
Project stageUnder construction
PlanningAug 2021 (completed)
ConsentedOct 2021 (completed)
ConstructionMay 2022 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2022-05-31.
Registered planning capacity; not measured generation.
SAS International, Unit 1 - Solar PV Panels is a 0.8 MW solar farm project in Wales. The applicant or operator on record is SAS International Limited. It is recorded as under construction since May 2022. The determining authority is Bridgend, reference P/21/765/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.800 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
SAS International Limited
Owner / operator
SAS International Limited
Year consented
2021
Construction started
2022
Location
SAS International Parc Crescent Waterton Industrial Estate, Bridgend, Mid Glamorgan, CF31 3XU