Electrical Substation North of, 314-316 Sandyhurst Lane, Kent, TN25 4PD
Sandyhurst Lane, Boughton Aluph - Energy Storage Facility is a 0.2 MW battery storage project in South East. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority isβ¦
Consented / Approved
Project stageConsented
PlanningNov 2024 (completed)
ConsentedJul 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-11-07.
Registered planning capacity; not measured generation.
Sandyhurst Lane, Boughton Aluph - Energy Storage Facility is a 0.2 MW battery storage project in South East. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is Ashford, reference PA/2024/2093.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.200 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
AMP Clean Energy
Owner / operator
AMP Clean Energy
Year consented
2025
Location
Electrical Substation North of, 314-316 Sandyhurst Lane, Kent, TN25 4PD