Sandyforth Farm, Ashton Road - Battery Energy Storage

Sandyforth Farm, Ashton Road, Billinge, Wigan, Greater Manchester, WN5 7XZ

Sandyforth Farm, Ashton Road - Battery Energy Storage is a 70 MW battery storage project in North West. The applicant or operator on record is UKGEA. Planning permission has been granted as of February 2025 and it is awaiting construction. The determining authority is Wigan, refe…

Consented / Approved
Project stageConsented
  1. PlanningFeb 2024 (completed)
  2. ConsentedFeb 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-04-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

70.000 MW
Power Capacity

πŸ“‹ Project Overview

Sandyforth Farm, Ashton Road - Battery Energy Storage is a 70 MW battery storage project in North West. The applicant or operator on record is UKGEA. Planning permission has been granted as of February 2025 and it is awaiting construction. The determining authority is Wigan, reference A/23/96568/MAJOR.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)70.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperUKGEA
Owner / operatorUKGEA
Year consented2025
LocationSandyforth Farm, Ashton Road, Billinge, Wigan, Greater Manchester, WN5 7XZ
RegionNorth West
Coordinates53.5107876Β°N, 2.6824845Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-02-07
2025-02-25