Land Adjacent To, Salisbury Substation, Wilton, Salisbury,, Wiltshire, SP2 0BL
Salisbury Substation is a 49.5 MW battery storage project in South West. The applicant or operator on record is SSE Renewables. It is recorded as operational since April 2024. The determining authority is Wiltshire, reference 19/05443/FUL.β¦
OperationalΒ· Since 2024
Project stageOperating
PlanningAug 2019 (completed)
ConsentedDec 2021 (completed)
ConstructionSep 2022 (completed)
OperatingApr 2024 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-06-04.
Registered planning capacity; not measured generation.
Salisbury Substation is a 49.5 MW battery storage project in South West. The applicant or operator on record is SSE Renewables. It is recorded as operational since April 2024. The determining authority is Wiltshire, reference 19/05443/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.500 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
SSE Renewables
Owner / operator
SSE Renewables
Year consented
2021
Construction started
2022
Commissioned / target
2024
Location
Land Adjacent To, Salisbury Substation, Wilton, Salisbury,, Wiltshire, SP2 0BL