πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Salford Refuse Treatment Plant (AD)

Cobden Street, Salford, Greater Manchester, M6 6NA

Salford Refuse Treatment Plant (AD) is a 2 MW bioenergy / waste project in North West. The applicant or operator on record is Viridor. It is recorded as operational since November 2013. The determining authority is Salford, reference 07/55275/FUL.…

Operational Β· Since 2013
Project stageOperating
  1. PlanningAug 2007 (completed)
  2. ConsentedMar 2008 (completed)
  3. ConstructionNov 2010 (completed)
  4. OperatingNov 2013 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2014-03-12.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity
2013
Commissioned

πŸ“‹ Project Overview

Salford Refuse Treatment Plant (AD) is a 2 MW bioenergy / waste project in North West. The applicant or operator on record is Viridor. It is recorded as operational since November 2013. The determining authority is Salford, reference 07/55275/FUL.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperViridor
Owner / operatorViridor
Year consented2008
Construction started2010
Commissioned / target2013
LocationCobden Street, Salford, Greater Manchester, M6 6NA
RegionNorth West
Coordinates53.4953491Β°N, 2.2873223Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2007-08-15
2008-03-06
2010-11-01
2013-11-30