πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Rye Common Lane

Blue Bell Lodge, Rye Common Lane, Crondall, Farnham, Surrey, Hampshire, GU10 5DE

Rye Common Lane is a 49.5 MW battery storage project in South East. The applicant or operator on record is Harmony Energy. The scheme is currently in the planning system, submitted May 2018. The determining authority is Hart, reference 18/01114/FUL.…

In Planning
50 MW
Power Capacity

πŸ“‹ Project Overview

Rye Common Lane is a 49.5 MW battery storage project in South East. The applicant or operator on record is Harmony Energy. The scheme is currently in the planning system, submitted May 2018. The determining authority is Hart, reference 18/01114/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHarmony Energy
Owner / operatorHarmony Energy
LocationBlue Bell Lodge, Rye Common Lane, Crondall, Farnham, Surrey, Hampshire, GU10 5DE
RegionSouth East
Coordinates51.2498507Β°N, 0.8755132Β°W

πŸ“… Project Timeline