Battery Storage

Rye Common Lane

Blue Bell Lodge, Rye Common Lane, Crondall, Farnham, Surrey, Hampshire, GU10 5DE

Rye Common Lane is a 49.5 MW battery storage project in South East. The applicant or operator on record is Harmony Energy. The scheme is currently in the planning system, submitted May 2018. The determining authority is Hart, reference 18/01114/FUL.…

Revised
Project stageSuperseded by a new application
  1. PlanningMay 2018 (completed)
  2. Superseded by a new application (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2023-09-14.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.500 MW
Power Capacity

πŸ“‹ Project Overview

Rye Common Lane is a 49.5 MW battery storage project in South East. The applicant or operator on record is Harmony Energy. The scheme is currently in the planning system, submitted May 2018. The determining authority is Hart, reference 18/01114/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.500 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHarmony Energy
Owner / operatorHarmony Energy
LocationBlue Bell Lodge, Rye Common Lane, Crondall, Farnham, Surrey, Hampshire, GU10 5DE
RegionSouth East
Coordinates51.2498507Β°N, 0.8755132Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (New REPD Ref)7737

πŸ“… Project Timeline

2018-05-23