Rushy Mead (University of Reading) is a 12 MW onshore wind project in South East. The applicant or operator on record is Partnerships for Renewables/University of Reading. The planning application was refused. The determining authority is Wokingham, reference F/2010/2266.…

Refused
Project stageRefused
  1. PlanningOct 2010 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2011-10-24.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

12.000 MW
Registered Capacity

πŸ“‹ Project Overview

Rushy Mead (University of Reading) is a 12 MW onshore wind project in South East. The applicant or operator on record is Partnerships for Renewables/University of Reading. The planning application was refused. The determining authority is Wokingham, reference F/2010/2266.

Site Schematic

SOUTH EAST Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)12.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPartnerships for Renewables/University of Reading
Owner / operatorPartnerships for Renewables/University of Reading
LocationRushy Mead, South of Reading (University owned land), Berkshire
RegionSouth East
Coordinates51.4164949Β°N, 0.9217327Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)3
No. of Turbines4

πŸ“… Project Timeline

2010-10-08