Rusholme Grange, Rusholme Lane, Drax, Selby, North Yorkshire, YO8 8PW
Rusholme Grange is a 40 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Storage. It is recorded as operational since August 2024. The determining authority is North Yorkshire, reference 2021/0601/FUL.β¦
OperationalΒ· Since 2024
Project stageOperating
PlanningMay 2021 (completed)
ConsentedSep 2021 (completed)
ConstructionJan 2022 (completed)
OperatingAug 2024 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2024-08-23.
Registered planning capacity; not measured generation.
Rusholme Grange is a 40 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Storage. It is recorded as operational since August 2024. The determining authority is North Yorkshire, reference 2021/0601/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
40.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Harmony Energy Storage
Owner / operator
Harmony Energy Storage
Year consented
2021
Construction started
2022
Commissioned / target
2024
Location
Rusholme Grange, Rusholme Lane, Drax, Selby, North Yorkshire, YO8 8PW