Royal Oak Way South - Solar Array is a 1.66 MW solar farm project in East Midlands. The applicant or operator on record is Cummins Limited. It is recorded as operational since October 2023. The determining authority is West Northamptonshire, reference WND/2022/0151.…

Operational Β· Since 2023
Project stageOperating
  1. PlanningFeb 2022 (completed)
  2. ConsentedMay 2022 (completed)
  3. ConstructionApr 2023 (completed)
  4. OperatingOct 2023 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2022-03-11.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.660 MW
Registered Capacity
2023
Commissioned

πŸ“‹ Project Overview

Royal Oak Way South - Solar Array is a 1.66 MW solar farm project in East Midlands. The applicant or operator on record is Cummins Limited. It is recorded as operational since October 2023. The determining authority is West Northamptonshire, reference WND/2022/0151.

Site Schematic

SUBSTATION ? ha Β· 1.66 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.660 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCummins Limited
Owner / operatorCummins Limited
Year consented2022
Construction started2023
Commissioned / target2023
LocationCummins Engine Company Ltd, Royal Oak Way South, Daventry, Northamptonshire, NN11 8NU
RegionEast Midlands
Coordinates52.2621292Β°N, 1.1777312Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)10047.42

πŸ“… Project Timeline

2022-02-22
2022-05-24
2023-04-01
2023-10-01