Adjacent Cellarhead Substation, Rownall Road, Wetley Rocks, Staffordshire, ST9 0BT

Rownall Road, Wetley Rocks - Battery Storage is a 2.6 MW battery storage project in West Midlands. The applicant or operator on record is Sirius Renewable Energy Limited. The scheme is currently in the planning system, submitted February 2022. The determining authority is Staffor…

Revised
Project stageSuperseded by a new application
  1. PlanningFeb 2022 (completed)
  2. Superseded by a new application (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2022-02-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.600 MW
Power Capacity

πŸ“‹ Project Overview

Rownall Road, Wetley Rocks - Battery Storage is a 2.6 MW battery storage project in West Midlands. The applicant or operator on record is Sirius Renewable Energy Limited. The scheme is currently in the planning system, submitted February 2022. The determining authority is Staffordshire Moorlands, reference SMD/2022/0047.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.600 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSirius Renewable Energy Limited
Owner / operatorSirius Renewable Energy Limited
LocationAdjacent Cellarhead Substation, Rownall Road, Wetley Rocks, Staffordshire, ST9 0BT
RegionWest Midlands
Coordinates53.0459644Β°N, 2.0743015Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (New REPD Ref)12448

πŸ“… Project Timeline