Long Lane, Tilesford, Pershore, Worcestershire, Hereford and Worcester, WR10 2LA
Rotherdale Farm is a 5 MW solar farm project in West Midlands. The applicant or operator on record is Vale Green Energy. It is recorded as operational since January 2015. The determining authority is Wychavon, reference 12/02528.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningNov 2012 (completed)
ConsentedJan 2013 (completed)
ConstructionNov 2014 (completed)
OperatingJan 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2013-05-21.
Registered planning capacity; not measured generation.
Rotherdale Farm is a 5 MW solar farm project in West Midlands. The applicant or operator on record is Vale Green Energy. It is recorded as operational since January 2015. The determining authority is Wychavon, reference 12/02528.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Vale Green Energy
Owner / operator
Vale Green Energy
Year consented
2013
Construction started
2014
Commissioned / target
2015
Location
Long Lane, Tilesford, Pershore, Worcestershire, Hereford and Worcester, WR10 2LA