πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Rookwood Way - Solar Farm

11A Rookwood Way, Suffolk, CB9 8PB

Rookwood Way - Solar Farm is a 2.04 MW solar farm project in Eastern. The applicant or operator on record is Sanofi UK. It is recorded as operational since May 2024. The determining authority is West Suffolk, reference DC/23/0052/FUL.…

Operational Β· Since 2024
Project stageOperating
  1. PlanningFeb 2023 (completed)
  2. ConsentedJun 2023 (completed)
  3. Construction (completed)
  4. OperatingMay 2024 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2024-05-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.040 MW
Registered Capacity
2024
Commissioned

πŸ“‹ Project Overview

Rookwood Way - Solar Farm is a 2.04 MW solar farm project in Eastern. The applicant or operator on record is Sanofi UK. It is recorded as operational since May 2024. The determining authority is West Suffolk, reference DC/23/0052/FUL.

Site Schematic

SUBSTATION ? ha Β· 2.04 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.040 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSanofi UK
Owner / operatorSanofi UK
Year consented2023
Commissioned / target2024
Location11A Rookwood Way, Suffolk, CB9 8PB
RegionEastern
Coordinates52.0755688Β°N, 0.4375979Β°E

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)21200

πŸ“… Project Timeline

2023-02-03
2023-06-29
2024-05-01