Land To East Of Balsillie Avenue And To The South Of The Limekilns Glenrothes, Fife, KY6 3ET
Roaring Hill (Resubmission) is a 30 MW battery storage project in Scotland. The applicant or operator on record is Renewable Energy Systems (RES). The scheme is currently in the planning system, submitted October 2017. The determining authority is Fife, reference 17/03318/FULL.β¦
Revised
Project stageSuperseded by a new application
PlanningOct 2017 (completed)
Superseded by a new application (project stopped here)
ConsentedDec 2017 (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Revised.
Official register: July 2026
Recorded status: Revised. Source record updated 2023-01-24.
Registered planning capacity; not measured generation.
Roaring Hill (Resubmission) is a 30 MW battery storage project in Scotland. The applicant or operator on record is Renewable Energy Systems (RES). The scheme is currently in the planning system, submitted October 2017. The determining authority is Fife, reference 17/03318/FULL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
30.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Renewable Energy Systems (RES)
Owner / operator
Renewable Energy Systems (RES)
Year consented
2017
Location
Land To East Of Balsillie Avenue And To The South Of The Limekilns Glenrothes, Fife, KY6 3ET