Land north of Roanhead Farm Hawthwaite Lane Barrow-in-Furness LA14 4QL, Cumbria
Roanhead Farm is a 6.5 MW solar farm project in North West. The applicant or operator on record is Fengate Capital. It is recorded as operational since March 2015. The determining authority is Westmorland and Furness, reference B03/2014/0473.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningJul 2014 (completed)
ConsentedSep 2014 (completed)
ConstructionJan 2015 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-12-17.
Registered planning capacity; not measured generation.
Roanhead Farm is a 6.5 MW solar farm project in North West. The applicant or operator on record is Fengate Capital. It is recorded as operational since March 2015. The determining authority is Westmorland and Furness, reference B03/2014/0473.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
6.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Fengate Capital
Owner / operator
Fengate Capital
Year consented
2014
Construction started
2015
Commissioned / target
2015
Location
Land north of Roanhead Farm Hawthwaite Lane Barrow-in-Furness LA14 4QL, Cumbria