πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Riverside Energy Park (REP)

Norman Rd, Belvedere, Bexley, London, DA17 6JY

Riverside Energy Park (REP) is a 80.5 MW bioenergy / waste project in London. The applicant or operator on record is Cory Riverside Energy. It is recorded as under construction since January 2023. The determining authority is The Planning Inspectorate - National Infrastructure, r…

Under Construction
Project stageUnder construction
  1. PlanningNov 2018 (completed)
  2. ConsentedApr 2020 (completed)
  3. ConstructionJan 2023 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2026-07-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

80.500 MW
Registered Capacity

πŸ“‹ Project Overview

Riverside Energy Park (REP) is a 80.5 MW bioenergy / waste project in London. The applicant or operator on record is Cory Riverside Energy. It is recorded as under construction since January 2023. The determining authority is The Planning Inspectorate - National Infrastructure, reference EN010093.

πŸ”§ Technical Specifications

Capacity (MW)80.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCory Riverside Energy
Owner / operatorCory Riverside Energy
Year consented2020
Construction started2023
LocationNorman Rd, Belvedere, Bexley, London, DA17 6JY
RegionLondon
Coordinates51.504508Β°N, 0.1533023Β°E

Additional published register fields

Registered technologyEfW Incineration
Storage Co-location REPD Ref ID7036

πŸ“… Project Timeline

2018-11-16
2020-04-09
2023-01-01