Riverdale Paper Plc, Earlsway, Gateshead, Tyne And Wear, NE11 0RQ
Riverdale Paper, Earlsway - Solar Panels is a 0.22 MW solar farm project in North East. The applicant or operator on record is Riverdale Waste Paper Limited. Planning permission has been granted as of November 2022 and it is awaiting construction. The determining authority is Gatβ¦
Consented / Approved
Project stageConsented
PlanningOct 2022 (completed)
ConsentedNov 2022 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2022-11-18.
Registered planning capacity; not measured generation.
Riverdale Paper, Earlsway - Solar Panels is a 0.22 MW solar farm project in North East. The applicant or operator on record is Riverdale Waste Paper Limited. Planning permission has been granted as of November 2022 and it is awaiting construction. The determining authority is Gateshead, reference DC/22/01142/NPA.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.220 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Riverdale Waste Paper Limited
Owner / operator
Riverdale Waste Paper Limited
Year consented
2022