πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Richborough Energy Park

Richborough Energy Park, Kent, CT13 9NL

Richborough Energy Park is a 49.9 MW battery storage project in South East. The applicant or operator on record is Richborough Energy Park Limited. It is recorded as operational since December 2023. The determining authority is Thanet, reference F/TH/20/1467.…

Operational Β· Since 2023
50 MW
Power Capacity
2023
Commissioned

πŸ“‹ Project Overview

Richborough Energy Park is a 49.9 MW battery storage project in South East. The applicant or operator on record is Richborough Energy Park Limited. It is recorded as operational since December 2023. The determining authority is Thanet, reference F/TH/20/1467.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperRichborough Energy Park Limited
Owner / operatorRichborough Energy Park Limited
Year consented2021
Commissioned / target2023
LocationRichborough Energy Park, Kent, CT13 9NL
RegionSouth East
Coordinates51.3119598Β°N, 1.3429997Β°E

πŸ“… Project Timeline