Rhydypandy Road, Morriston - Battery Energy Storage System is a 100 MW battery storage project in Wales. The applicant or operator on record is Statkraft UK. Planning permission has been granted as of December 2025 and it is awaiting construction. The determining authority is Swa…

Consented / Approved
Project stageConsented
  1. PlanningApr 2025 (completed)
  2. ConsentedDec 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-01-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

100.000 MW
Power Capacity

πŸ“‹ Project Overview

Rhydypandy Road, Morriston - Battery Energy Storage System is a 100 MW battery storage project in Wales. The applicant or operator on record is Statkraft UK. Planning permission has been granted as of December 2025 and it is awaiting construction. The determining authority is Swansea, reference 2025/0855/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)100.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperStatkraft UK
Owner / operatorStatkraft UK
Year consented2025
LocationW/O Rhydypandy Road, Morriston, Swansea, West Glamorgan, SA6
RegionWales
Coordinates51.5833302Β°N, 3.7499962Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2025-04-22
2025-12-18