Redlands Farm is a 6.2 MW solar farm project in South West. The applicant or operator on record is juwi Renewable Energies. It is recorded as operational since February 2015. The determining authority is Somerset, reference 2013/1189.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningJun 2013 (completed)
ConsentedNov 2013 (completed)
ConstructionSep 2014 (completed)
OperatingFeb 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-06-16.
Registered planning capacity; not measured generation.
Redlands Farm is a 6.2 MW solar farm project in South West. The applicant or operator on record is juwi Renewable Energies. It is recorded as operational since February 2015. The determining authority is Somerset, reference 2013/1189.