Redhill 2 is a 3 MW bioenergy / waste project in South East. The applicant or operator on record is Biffa. It is recorded as operational since December 2001. The determining authority is Tandridge.…

Operational Β· Since 2001
Project stageOperating
  1. PlanningJul 1999 (completed)
  2. ConsentedNov 1999 (completed)
  3. Construction (completed)
  4. OperatingDec 2001 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-12-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

3.000 MW
Registered Capacity
2001
Commissioned

πŸ“‹ Project Overview

Redhill 2 is a 3 MW bioenergy / waste project in South East. The applicant or operator on record is Biffa. It is recorded as operational since December 2001. The determining authority is Tandridge.

πŸ”§ Technical Specifications

Capacity (MW)3.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBiffa
Owner / operatorBiffa
Year consented1999
Commissioned / target2001
LocationCormongers Lane, Nutfield, Nr Redhill, Surrey, Surrey
RegionSouth East
Coordinates51.2353963Β°N, 0.1464371Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1999-07-22
1999-11-01
2001-12-10