Rassau Industrial Estate is a 6 MW battery storage project in Wales. The applicant or operator on record is Private Developer. It is recorded as under construction since July 2021. The determining authority is Blaenau Gwent, reference C/2019/0326.…

Under Construction
Project stageUnder construction
  1. PlanningNov 2019 (completed)
  2. ConsentedJan 2020 (completed)
  3. ConstructionJul 2021 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2022-01-11.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.000 MW
Power Capacity

πŸ“‹ Project Overview

Rassau Industrial Estate is a 6 MW battery storage project in Wales. The applicant or operator on record is Private Developer. It is recorded as under construction since July 2021. The determining authority is Blaenau Gwent, reference C/2019/0326.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPrivate Developer
Owner / operatorPrivate Developer
Year consented2020
Construction started2021
LocationUnit 16, Rassau Industrial Estate, Rassau, Ebbw Vale, Blaenau Gwent, NP23 5SD
RegionWales
Coordinates51.8033429Β°N, 3.2332502Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2019-11-25
2020-01-22
2021-07-16