πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Ramsgate Sports Centre, High Street - Solar Panels & Battery Storage

Ramsgate Sports Centre, High Street, Ramsgate, Kent, CT11 9TT

Ramsgate Sports Centre, High Street - Solar Panels & Battery Storage is a 0.4 MW battery storage project in South East. The applicant or operator on record is Thanet District Council. Planning permission has been granted as of April 2025 and it is awaiting construction. The deter…

Consented / Approved
Project stageConsented
  1. PlanningFeb 2025 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-05-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.400 MW
Power Capacity

πŸ“‹ Project Overview

Ramsgate Sports Centre, High Street - Solar Panels & Battery Storage is a 0.4 MW battery storage project in South East. The applicant or operator on record is Thanet District Council. Planning permission has been granted as of April 2025 and it is awaiting construction. The determining authority is Thanet, reference F/TH/25/0057.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.400 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperThanet District Council
Owner / operatorThanet District Council
Year consented2025
LocationRamsgate Sports Centre, High Street, Ramsgate, Kent, CT11 9TT
RegionSouth East
Coordinates51.3368477Β°N, 1.4134687Β°E

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID18274

πŸ“… Project Timeline

2025-02-13
2025-04-25