Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD) - extension

Ings Road, Bentley, Doncaster,, South Yorkshire, DN5 9SW

Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD) - extension is a 3 MW bioenergy / waste project in Yorkshire and Humber. The applicant or operator on record is Prosper Demulder / ReFood. It is recorded as operational since June 2015. The determining authority is Don…

Operational Β· Since 2015
Project stageOperating
  1. PlanningAug 2013 (completed)
  2. ConsentedNov 2013 (completed)
  3. ConstructionMar 2014 (completed)
  4. OperatingJun 2015 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-06-22.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

3.000 MW
Registered Capacity
2015
Commissioned

πŸ“‹ Project Overview

Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD) - extension is a 3 MW bioenergy / waste project in Yorkshire and Humber. The applicant or operator on record is Prosper Demulder / ReFood. It is recorded as operational since June 2015. The determining authority is Doncaster, reference 13/01843/FULMC.

πŸ”§ Technical Specifications

Capacity (MW)3.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperProsper Demulder / ReFood
Owner / operatorProsper Demulder / ReFood
Year consented2013
Construction started2014
Commissioned / target2015
LocationIngs Road, Bentley, Doncaster,, South Yorkshire, DN5 9SW
RegionYorkshire and Humber
Coordinates53.5369169Β°N, 1.1374336Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2013-08-30
2013-11-20
2014-03-18
2015-06-02