Operational Β· Since 2011
Project stageOperating
  1. PlanningAug 2008 (completed)
  2. ConsentedFeb 2009 (completed)
  3. ConstructionApr 2011 (completed)
  4. OperatingSep 2011 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2014-01-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity
2011
Commissioned

πŸ“‹ Project Overview

Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD) is a 2 MW bioenergy / waste project in Yorkshire and Humber. The applicant or operator on record is Prosper Demulder / ReFood. It is recorded as operational since September 2011. The determining authority is Doncaster, reference 08/02575/FULM.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperProsper Demulder / ReFood
Owner / operatorProsper Demulder / ReFood
Year consented2009
Construction started2011
Commissioned / target2011
LocationIngs Road, Bentley, Doncaster,, South Yorkshire, DN5 9SW
RegionYorkshire and Humber
Coordinates53.5369169Β°N, 1.1374336Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2008-08-27
2009-02-17
2011-04-01
2011-09-09