πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Portsmouth ERF

Portsmouth Incinerator, Quartremaine Road, Copnor, Portsmouth, Hampshire, Hampshire

Portsmouth ERF is a 14 MW bioenergy / waste project in South East. The applicant or operator on record is Veolia. It is recorded as operational since March 2005. The determining authority is Portsmouth, reference A*29026/AF.…

Operational Β· Since 2005
Project stageOperating
  1. PlanningAug 1998 (completed)
  2. ConsentedOct 2001 (completed)
  3. Construction (completed)
  4. OperatingMar 2005 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2010-04-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

14.000 MW
Registered Capacity
2005
Commissioned

πŸ“‹ Project Overview

Portsmouth ERF is a 14 MW bioenergy / waste project in South East. The applicant or operator on record is Veolia. It is recorded as operational since March 2005. The determining authority is Portsmouth, reference A*29026/AF.

πŸ”§ Technical Specifications

Capacity (MW)14.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperVeolia
Owner / operatorVeolia
Year consented2001
Commissioned / target2005
LocationPortsmouth Incinerator, Quartremaine Road, Copnor, Portsmouth, Hampshire, Hampshire
RegionSouth East
Coordinates50.821979Β°N, 1.0542247Β°W

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

1998-08-14
2001-10-15
2005-03-01