πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Portley Ford Landfill Site

Portley Ford Welford Cold Ashby Northants, Northamptonshire

Portley Ford Landfill Site is a 1.8 MW bioenergy / waste project in East Midlands. The applicant or operator on record is Biogeneration / Biffa. It is recorded as operational since October 1996. The determining authority is West Northamptonshire.…

Operational Β· Since 1996
Project stageOperating
  1. PlanningMay 1994 (completed)
  2. ConsentedFeb 1995 (completed)
  3. Construction (completed)
  4. OperatingOct 1996 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2004-12-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.800 MW
Registered Capacity
1996
Commissioned

πŸ“‹ Project Overview

Portley Ford Landfill Site is a 1.8 MW bioenergy / waste project in East Midlands. The applicant or operator on record is Biogeneration / Biffa. It is recorded as operational since October 1996. The determining authority is West Northamptonshire.

πŸ”§ Technical Specifications

Capacity (MW)1.800 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBiogeneration / Biffa
Owner / operatorBiogeneration / Biffa
Year consented1995
Commissioned / target1996
LocationPortley Ford Welford Cold Ashby Northants, Northamptonshire
RegionEast Midlands
Coordinates52.387072Β°N, 1.0331341Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1994-05-10
1995-02-08
1996-10-01