Battery Storage

Portadown Road

Land @ & 100m S/E of, 87 Portadown Road, Immediately adjacent to NIE, Craigavon, Co Armagh, Co. Armagh, BT62 2BB

Portadown Road is a 50 MW battery storage project in Northern Ireland. The applicant or operator on record is Low Carbon Storage Ireland. It is recorded as under construction since January 2020. The determining authority is Armagh City, Banbridge and Craigavon, reference LA08/201…

Under Construction
Project stageUnder construction
  1. PlanningJun 2018 (completed)
  2. Consented (completed)
  3. ConstructionJan 2020 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2020-06-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.000 MW
Power Capacity

πŸ“‹ Project Overview

Portadown Road is a 50 MW battery storage project in Northern Ireland. The applicant or operator on record is Low Carbon Storage Ireland. It is recorded as under construction since January 2020. The determining authority is Armagh City, Banbridge and Craigavon, reference LA08/2018/0851/F.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLow Carbon Storage Ireland
Owner / operatorLow Carbon Storage Ireland
Construction started2020
LocationLand @ & 100m S/E of, 87 Portadown Road, Immediately adjacent to NIE, Craigavon, Co Armagh, Co. Armagh, BT62 2BB
RegionNorthern Ireland
Coordinates54.3701899Β°N, 6.42882Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2018-06-18
2020-01-15